Renovation

November 24, 2019 - The progress shown here are foundations being placed for the cafeteria and last foundations of the project; the exterior wall framing started on the classroom addition; and the gymnasium expansion roof structure is complete

November 8, 2019 - Steel has gone up for the classroom and band room areas, foundation prep ongoing for the cafeteria addition, and a new grease trap being installed.

November 1, 2019 - Steel being erected.





October 31, 2019 - Prepping for the slab on grade at the classroom wing including under slab piping, vapor barrier, insulation and reinforcing. Also the roof bar joists have arrived for the gym expansion and the fire wall is being constructed between existing school and classroom addition.

October 10, 2019 - Winslow School Project Update: Masonry for the gymnasium expansion is nearing completion with topping off expected by the end of the week. Underground plumbing at the classroom wing is being installed and foundation at the Band addition is being insulated

Masonry for Gym

Masonry for Gym

Underground Plumbing

Foundation for Band Room Addition

September 26, 2019 - Crews are taking advantage of the weather and have completed the foundation for the classroom wing and are now moving on to the band room addition.

Dirt and the beginnings of a foundation
Backhoe
Construction workers pouring cement into a form